| Lake Edge, Puchong Waterville (Phase 1) Progress On Site February 2009 Page 1 2 > |
||||
![]() |
![]() |
|||
| Row 1 (Jalan LE 3/4) Lot No. 1406 & 1407, 1408 & 1409, 1410 & 1411 Construction works for letter box and utility compartment is well underway. |
Row 2 (Jalan LE 1/1) Lot No. 1412 & 1413 Varnishing of timber floor is in progress. |
|||
![]() |
![]() |
|||
| Row 2 (Jalan LE 1/1) Lot No. 1414 & 1415 Installation of timber flooring for staircase is in progress. |
Row 2 (Jalan LE 1/1) Lot No. 1416 & 1417, 1422 & 1423 Installation of glass railing on balcony (1st & 2nd floor) is in progress. |
|||
|
||||